A thermal process within a facility rejects 10,000 lbm/hr of hot water (T out = 190F). An

Question:

A thermal process within a facility rejects 10,000 lbm/hr of hot water (Tout = 190°F). An energy audit of the facility revealed that instead of using an open water system, which feeds fresh cold water (Tin = 55°F) to the boiler, a closed-loop water system can be set up (with a total cost of $90,000) to reuse the hot water wasted by the facility at the end of the thermal process, as depicted in the sketch below. Determine the simple payback period for the closed-loop installation if the cost of fuel is $6/MMBtu and the boiler efficiency is 80 percent. Assume that the facility is operated 4,000 hours per year.image text in transcribedimage text in transcribed