Question: 19. An IT support group at Thomson State College has seven projects to complete. The time in days and project deadlines are shown next. Project
19. An IT support group at Thomson State College has seven projects to complete.
The time in days and project deadlines are shown next.
Project 1 2 3 4 5 6 7 Time 4 9 12 16 9 15 8 Deadline 12 24 60 28 24 36 48
a. Sequence the projects to minimize the average lateness.
b. Sequence the projects to minimize the average tardiness.
c. Compare these solutions to the SPT and EDD rules.