Ricky Wilcox contracted with Fireside Log Homes to build a house. The logs were to be delivered

Question:

Ricky Wilcox contracted with Fireside Log Homes to build a house. The logs were to be delivered precut and predrilled, but they arrived unfinished. Fireside told Wilcox that cutting and drilling the logs would take only two or three days. In fact, this process slowed the project by five months. To cover costs caused by the delay Wilcox borrowed an additional $200,000. When the house was finally built, he filed a suit against Fireside. Did Fireside commit fraud? Explain. [Esprit Log and Timber Frame Homes, Inc. v. Wilcox, 302 Ga.App. 550, 691 S.E.2d 344 (2010)]