=+e) Is this process out of control? Hour No. of Defects Sample Size 1 11 200 2

Question:

=+e) Is this process out of control?

Hour No. of Defects Sample Size 1 11 200 2 9 200 3 17 200 4 19 200 5 15 200 6 15 200 7 18 200 8 21 200 9 18 200 10 6 200 11 27 200 12 14 200 13 7 200 14 18 200 15 19 200 16 18 200 17 17 200 18 15 200 19 7 200 20 16 200