Question: Refer to problem 18.20 on page 726 concerning waiting time for customers at a bank. Suppose management has set an upper specification limit of 5
Refer to problem 18.20 on page 726 concerning waiting time for customers at a bank. Suppose management has set an upper specification limit of 5 minutes on waiting time and that at least 99% of the waiting times must be less than 5 minutes in order for the process to be considered capable.
< BANK_TIME >
a. Estimate the percentage of waiting times that are inside the specification limits. Is the process capable of meeting the company policy?
b. If management implemented a new policy stating that 99.7% of all waiting times are required to be within specifications, is this process capable of reaching that goal? Explain.