For the record with a ProjectLineItemID value of 7, why does the Factor field contain 1.3? a.

Question:

For the record with a ProjectLineItemID value of 7, why does the Factor field contain 1.3?

a. It represents an estimated increase of 1.3% due to risk or complexity for that task.

b. It represents an estimated increase of 30% due to risk or complexity for that task.

c. It represents an estimate of 1.3 hours for that task.

d. It represents an additional 1.3 hours to add to the task.