A product owner calls the Scrum master and requests to see the remaining work effort for the

Question:

A product owner calls the Scrum master and requests to see the remaining work effort for the sprint. What is the Scrum master likely to show the product owner in response?

A. A bubble chart B. A status report C. A burndown chart D. A sprint summary chart