A project is being managed by a project manager. A large portion of the work of the
Question:
A project is being managed by a project manager. A large portion of the work of the project is being subcontracted to an outside vendor. During the project it is found that a significant change in the design of the project is necessary. The project manager should:
a. Issue a change notice to the contractor immediately.
b. Issue a purchase order to investigate the change.
c. Notify the contractor of the design change possibility.
d. Rebid the contract.
Fantastic news! We've Found the answer you've been seeking!
Step by Step Answer:
Related Book For
Preparing For The Project Management Professional (PMP Certification Exam)
ISBN: 9780814471722
2nd Edition
Authors: Michael W. Newell PMP ENP
Question Posted: