A project manager is performing activities associated with the Plan Procurement Management process. He is attempting to
Question:
A project manager is performing activities associated with the Plan Procurement Management process. He is attempting to determine, along with the relevant subjectmatter experts, whether it makes more sense to develop internally or purchase a deliverable. What tools or methods can he use to produce a successful outcome?
A. Market research B. Advertising C. Source selection analysis D. Make-or-buy analysis