You are in the process of facilitating a change control meeting. You review a change request that

Question:

You are in the process of facilitating a change control meeting. You review a change request that would double the scope of the project but would not yield a major increase in the project’s resulting benefits. You know that the submitter of the change request has a tendency to bloat a project’s scope without fully thinking through the impact, but as a result of their position in the company, their changes tend to be approved. You invite a financial analyst to the meeting to walk the team through the negative impact of the change request, and the team votes to reject the change. What type of power did you use?

A. Legitimate B. Expert C. Referent D. Punishment