You are working on the communications management plan for your project and have considered the timing and
Question:
You are working on the communications management plan for your project and have considered the timing and need for updated information by you and your four stakeholders. Your organization has modern, up-to-date technology that your stakeholders and staff have used before, so you anticipate that supplying the information and updates to your stakeholders and team members will be a breeze. Which of the following is true?
A. There are 10 channels of communication, which should be considered when examining communications requirements analysis.
B. There are 5 channels of communication, which should be considered when examining communications requirements.
C. There are 12 channels of communication, which should be considered when examining communications technology.
D. There are 20 channels of communication, which should be considered when examining communications technology.