During WBS creation on a large, complex project, the product and project deliverables are broken down into

Question:

During WBS creation on a large, complex project, the product and project deliverables are broken down into progressively lower levels of detail.

Once the WBS has been defined at the second or third level of detail, whose input is essential in order to break down the work further?

a. sponsor

b. subject matter experts

c. internal stakeholders

d. external stakeholders