If your sponsor asks for an estimate as to how much more money your team needs to

Question:

If your sponsor asks for an estimate as to how much more money your team needs to complete all project work as scheduled, which of the following formulas might you use?

a. BAC 2 EAC

b. EV/PV

c. (BAC 2 EV)/CPI

d. (BAC 2 EV)/(EAC 2 AC)