Juan is a project manager for a project that has been baselined and is now under way.
Question:
Juan is a project manager for a project that has been baselined and is now under way. When a customer approaches Juan and asks him to increase the project’s scope, Juan’s response should be to _______________.
a. comply with the customer’s request if it seems reasonable
b. determine the schedule performance index (SPI)
c. perform integrated change control
d. calculate the Estimate to Complete (ETC)
Fantastic news! We've Found the answer you've been seeking!
Step by Step Answer:
Answer rating: 100% (3 reviews)
c perform integrated change control When a customer reque...View the full answer
Answered By
Aysha Ali
my name is ayesha ali. i have done my matriculation in science topics with a+ . then i got admission in the field of computer science and technology in punjab college, lahore. i have passed my final examination of college with a+ also. after that, i got admission in the biggest university of pakistan which is university of the punjab. i am studying business and information technology in my university. i always stand first in my class. i am very brilliant client. my experts always appreciate my work. my projects are very popular in my university because i always complete my work with extreme devotion. i have a great knowledge about all major science topics. science topics always remain my favorite topics. i am also a home expert. i teach many clients at my home ranging from pre-school level to university level. my clients always show excellent result. i am expert in writing essays, reports, speeches, researches and all type of projects. i also have a vast knowledge about business, marketing, cost accounting and finance. i am also expert in making presentations on powerpoint and microsoft word. if you need any sort of help in any topic, please dont hesitate to consult with me. i will provide you the best work at a very reasonable price. i am quality oriented and i have 5 year experience in the following field.
matriculation in science topics; inter in computer science; bachelors in business and information technology
_embed src=http://www.clocklink.com/clocks/0018-orange.swf?timezone=usa_albany& width=200 height=200 wmode=transparent type=application/x-shockwave-flash_
4.40+
11+ Reviews
14+ Question Solved
Related Book For
Contemporary Project Management
ISBN: 9780357715734
5th Edition
Authors: Timothy Kloppenborg, Vittal S. Anantatmula, Kathryn Wells
Question Posted:
Students also viewed these Business questions
-
Hyten Corporation On June 5, 1998, a meeting was held at Hyten Corporation, between Bill Knapp, Director of Marketing/Sales, and John Rich, director of engineering. The purpose of the meeting was to...
-
1. Charlie is a project manager for a new system under development for a national mortgage processing company. A common experience for IS managers today is to lose experienced IS staff members, who...
-
THIRD AVENUE SOFTWARE HEALTH-CARE APP PROJECT This case is new for the ninth edition of Information Technology Project Management . The case provides an opportunity to apply agile and Scrum...
-
What is the time value of money? Including present and future value. How would a financial expert interpret it?
-
Describe the main ancient Greek competitive character(s), and compare the ancient Olympics (as a festival featuring athletics) to the Olympics today, identifying any major differences. Explain what...
-
Question 5 (1 point) Jamison Insurance's stock currently sells for $15.00 a share. It just paid a dividend of $1.50 a share (that is, Do=$1.50). The dividend is expected to grow at a constant rate of...
-
Know what makes emerging markets attractive for international business. L01
-
Approximately 150SCFM (standard cubic feet per minute) of nitrogen is required by a process facility. As shown in the diagram below, plans call for supplying the facility from a tank of liquid...
-
Schedule of Activity Costs Quality Control Activities Activity Cost Process audits $50,200 Training of machine operators 27,400 Processing returned products 16,800 Scrap processing (disposal) 26,800...
-
Which of the following formulas represents the schedule performance index (SPI)? a. EV/PV b. EV 2 PV c. EV 2 AC d. EV/AC
-
In regard to Project Work, which activity refers to reviewing the progress and capturing project performance data with reference to the project plan, developing performance measures, and...
-
(a) If a rod of 1025 steel 0.5 m (19.7 in.) long is heated from 20 to 80C (68 to 176F) while its ends are maintained rigid, determine the type and magnitude of stress that develops. Assume that at...
-
Experiment 3 19. Now click on Circuit 5 and set the values for the Resistors and Voltage as follows: a. R1 =10.0 W, R2 = 20.0 W, R3 = 50.0 W, R4=50.0 W, V=10.0 V. b. Using the formula for adding...
-
This problem is based on the JA Tires data that was first introduced in problem 6-35. If you have not already accessed the data, it can be downloaded from the textbook website or from the attached...
-
Based in Miramichi, New Brunswick, Abenaki Associates Ltd. has been providing information and computer software technology to First Nation customers for more than thirty years. Abenaki Associates is...
-
a = [1,2,3,4] b= a -1 print(b) What is the output? The code does not make errors. Q3. (10 pts) What is the output? The code does not make errors. n=3 for k in range (n) : for m in range (k):...
-
Rodriguez Corporation issues 12,000 shares of its common stock for $62,000 cash on February 20. Prepare journal entries to record this event under each of the following separate situations. 1. The...
-
A gas is cooled and loses 82 J of heat. The gas contracts as it cools, and work done on the system equal to 29 J is exchanged with the surroundings. What are q, w, and U?
-
Data 9.2 on page 540 introduces the dataset Cereal, which includes information on the number of grams of fiber in a serving for 30 different breakfast cereals. The cereals come from three different...
-
What are the most important tools and technologies for safeguarding information resources? a) Name and describe three authentication methods. b) Describe the roles of firewalls, intrusion detection...
-
How do enterprise systems help businesses achieve operational excellence? a. Define an enterprise system and explain how enterprise software works. b. Describe how enterprise systems provide value...
-
How do supply chain management systems coordinate planning, production, and logistics with suppliers? a) Define a supply chain and identify each of its components. b) Explain how supply chain...
-
Fig 1. Rolling a 4 on a D4 A four sided die (D4), shaped like a pyramid (or tetrahedron), has 4 flat surfaces opposite four corner points. A number (1, 2, 3, or 4) appears close to the edge of each...
-
I just need help with question #4 please! Thank you! Windsor Manufacturing uses MRP to schedule its production. Below is the Bill of Material (BOM) for Product A. The quantity needed of the part...
-
(25) Suppose that we have an economy consisting of two farmers, Cornelius and Wheaton, who unsurprisingly farm corn c and wheat w, respectively. Assume that both farmers produce their crop of choice...
Study smarter with the SolutionInn App