The key factor that differentiates scope planning in plan-driven and agile projects is: a. Stewardship of assets

Question:

The key factor that differentiates scope planning in plan-driven and agile projects is:

a. Stewardship of assets

b. Uncertainty of requirements

c. Acceptance criteria

d. Stakeholder interviews