Using the information for Exercise 8.8, input the data into MS Project. Display and print the schedule
Question:
Using the information for Exercise 8.8, input the data into MS Project. Display and print the schedule in Gantt chart format, as shown in Exhibit 8.19
Exercise 8.8
Given the information below, create the project schedule network. Then, using the two-pass method, calculate and show the early and late starts and float for each activity and the critical path. Show the schedule on a Gantt chart showing critical and non-critical activities and float.
Fantastic news! We've Found the answer you've been seeking!
Step by Step Answer:
Related Book For
Contemporary Project Management
ISBN: 9780357715734
5th Edition
Authors: Timothy Kloppenborg, Vittal S. Anantatmula, Kathryn Wells
Question Posted: