You are planning the schedule and come to an activity that you are unfamiliar with. Your SMEs

Question:

You are planning the schedule and come to an activity that you are unfamiliar with. Your SMEs give you the following time estimates: most likely

= 5 hours; optimistic = 2 hours; pessimistic = 14 hours. Using PERT, which activity duration do you use in your plan?

a. 6 hours

b. 2 hours

c. 5 hours

d. 10 hours