Determining cost of land Obj. 1 On-Time Delivery Company acquired an adjacent lot to construct a new warehouse, paying $90,000 in cash and giving a short-term note for $50,000. Legal fees paid were $1,750, delinquent taxes assumed were $25,000, and fees paid to remove an old building from the land were $9,000. Materials salvaged from the demolition of the building were sold for $1,000. A contractor was paid $415,000 to construct a new warehouse. Determine the cost of the land to be reported on the balance sheet.