A) Utilizing another case study project, prepare a work package for direct labor for a system of

Question:

A) Utilizing another case study project, prepare a work package for direct labor for a system of work such as concrete foundations, CIP concrete walls, tilt-up concrete walls, or SOG. Attach the original portion of the estimate that refers to this work package. 

B) As an alternate to a separate case study project, the following quantity and man-hour columns can be used as a baseline estimate. Assume a three-person crew working for four months from start to completion for all of these activities:

Excavation: Formwork: Reinforcement steel or mesh: Concrete placement: Slab finish: 2 x 6 wall framing:

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Question Posted: