A) Utilizing another case study project, prepare a work package for direct labor for a system of
Question:
A) Utilizing another case study project, prepare a work package for direct labor for a system of work such as concrete foundations, CIP concrete walls, tilt-up concrete walls, or SOG. Attach the original portion of the estimate that refers to this work package.
B) As an alternate to a separate case study project, the following quantity and man-hour columns can be used as a baseline estimate. Assume a three-person crew working for four months from start to completion for all of these activities:
Fantastic news! We've Found the answer you've been seeking!
Step by Step Answer:
Related Book For
Cost Accounting And Financial Management For Construction Project Managers
ISBN: 9781138550650
1st Edition
Authors: Len Holm
Question Posted: