An effective cost control system controls costs prior to an event through >- establishment of budgets

Question:

An effective cost control system controls costs

• prior to an event through

>- establishment of budgets and standards.

other stated expectations of performance out¬ comes.

• during an event by

>■ correcting deviations from plans or budgets.

>■ monitoring other aspects of operations rela¬ tive to expectations.

• following an event by providing feedback on per¬ formance. LO.1