Assume that a company's production requires 400 pounds of steel each day, that it takes four days

Question:

Assume that a company's production requires 400 pounds of steel each day, that it takes four days to receive steel from the supplier, and that the company wants to have 400 pounds of steel on hand at all times. Calculate the reorder point.