Harrison, Inc., had the following quality costs for the years ended December 31, 2010 and 2011: At
Question:
Harrison, Inc., had the following quality costs for the years ended December 31, 2010 and 2011:
At the end of 2010, management decided to increase its investment in control costs by 50 percent for each category’s items with the expectation that failure costs would decrease by 20 percent for each item of the failure categories. Sales were $4,000,000 for both 2010 and 2011.
Required:
1. Calculate the budgeted costs for 2011, and prepare an interim quality performance report.
2. Comment on the significance of the report. How much progress has Harrison made?
3. What if sales were $4,000,000 for 2010 and $5,000,000 for 2011? What adjustment to budgeted rework costs would be made? Budgeted quality audits? Assuming the actual costs for 2011 do not change, what does this adjustment say about Harrison’s performance?LO1
Step by Step Answer:
Introduction To Cost Accounting
ISBN: 9780538749633
1st International Edition
Authors: Don R. Hansen, Maryanne Mowen, Liming Guan, Mowen/Hansen