How would the cash flow curve presented for Evergreen Construction Company change if: a. The project start

Question:

How would the cash flow curve presented for Evergreen Construction Company change if: 

a. The project start date was delayed for one month, 

b. All of the site improvements were re-scheduled to be accomplished during early shell construction rather than near the completion of the project, 

c. The swimming pool design was finalized and will cost $350,000 which is change ordered into the contract and will be installed during the last month of the schedule, or 

d. Retention will only be held on Evergreen’s subcontractors?

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Question Posted: