Jones Ltd. has a budgeted activity level of 50,000 direct labour hours and budgeted production overheads of Rs. 100,000. You are required to calculate the underabsorbed and overabsorbed overheads, giving reasons, if,
(a). 50,000 direct labour hours are worked and the actual overheads were Rs. 94,000.
(b). 43,000 direct labour hours are worked and the actual overheads were Rs. 100,000.
(c). 43,000 direct labour hours are worked and the actual overheads were Rs. 94,000.