Multiple regression results from the data of Yamahonda Motors Company (exercise 10-19) are as follows:
Assume that management predicts the materials cost to be $5,000 and machinehours to be 190 for the coming period.
Use the multiple regression results to prepare an estimate of overhead costs for the coming period.