The time taken for a particular operation for Operator X in the process division of a manufacturing

Question:

The time taken for a particular operation for Operator X in the process division of a manufacturing concern on three different counts was 24,22 and 27 minutes while that of Operator Y was 20, 23 and 26 minutes. It has been ascertained that the rating of X is 70/60 and that of Y is 55/60. Allowances for fatigue, and personal needs are assumed at 15%. Calculate, using the above information as a base for that particular operation,
(i) The standard time
(ii) The time allowed under an incentive allowance of 30% of standard time.