There are two piece-workers, Rakhal and Upendra, who are paid Rs. 5 for each piece work executed,

Question:

There are two piece-workers, Rakhal and Upendra, who are paid Rs. 5 for each piece work executed, which costs Rs. 15 per piece in materials.
In a working day of 8 hours, Rakhal can complete 4 pieces and Upendra only 3. If the overhead charges be Rs. 1.50 per hour show which of the two piece workers is more useful to the factory.