Cost indifference point The management of Land's Bottom mail order company is eval- uating methods of automating
Question:
Cost indifference point The management of Land's Bottom mail order company is eval- uating methods of automating the customer billing system with the intention of improving the collection time on receivables. The selection has been narrowed to two billing systems. Bill-Fast would require leasing equipment for $6,000 a month. A maintenance contract and other fixed costs would amount to another $2,000 a month. Monthly variable costs including forms and other supplies would cost $.35 per customer. Other variable costs such as labor cost to run the equipment would be $.15 per customer. Speed-O-Bill is a more sophisticated system that is much faster than the other. However, it is more costly to lease and maintain. The monthly lease cost for Speed-O-Bill is $15,000. Maintenance and other fixed costs are $5,000 a month. Monthly variable costs per customer would be $.30.
Step by Step Answer: