Following are the data obtained from the books of a manufacturing company with respect to variable overheads:
Question:
Following are the data obtained from the books of a manufacturing company with respect to variable overheads:
Budgeted production: 600 units.
Budgeted variable overhead: Rs. 15,600.
Standard time for 1 unit: 20 hours.
Actual production: 500 units.
Actual hours worked: 9,000 hrs.
Actual variable overhead: Rs. 14,000.
Compute variable-overhead variances?