From the following data of a factory machine room, you are required to compute an hourly machine
Question:
From the following data of a factory machine room, you are required to compute an hourly machine hour rate, assuming that the machine room will work at 90% capacity throughout the year and that a breakdown of 10% is reasonable.
There are three days holidays for Deepavali, two days for Christmas, two days for Holi, exclusive of Sundays.
The factory works for 8 hours a day and 4 hours on Saturdays.