NPV and cost of prediction error Mossley Corporation's marketing manager proposed the acquisition of laptop computers for

Question:

NPV and cost of prediction error Mossley Corporation's marketing manager proposed the acquisition of laptop computers for all sales representatives. The computers would simplify and speed up order processing and would produce cost savings of $10,000 per year. The total cost of the new computers is $23,000, including tax and delivery charges. There is an additional cost of $4,000 to train the sales representatives to use the computers. Each computer has a useful life of 5 years with no salvage value. The company evaluates capital projects using the net present value method with a 17 percent cost of capital.image text in transcribed