Order point Phoenix Company expects daily usage of 500 lbs. of material Z, an anticipated lead time
Question:
Order point Phoenix Company expects daily usage of 500 lbs. of material Z, an anticipated lead time of seven days, and a desired safety stock of 2,500 Ibs.
a. Determine the order point.
b. Determine the number of lbs. to be issued from safety stock if the new order is four days late.