Order point Phoenix Company expects daily usage of 500 lbs. of material Z, an anticipated lead time

Question:

Order point Phoenix Company expects daily usage of 500 lbs. of material Z, an anticipated lead time of seven days, and a desired safety stock of 2,500 Ibs.

a. Determine the order point.

b. Determine the number of lbs. to be issued from safety stock if the new order is four days late.

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

Principles Of Cost Accounting

ISBN: 9780324374179

14th Edition

Authors: Edward J. Vanderbeck

Question Posted: