S. Patak and Smelley Co. manufactures foot devices for athletes and dancers. They usually have to wait
Question:
S. Patak and Smelley Co. manufactures foot devices for athletes and dancers. They usually have to wait 4 weeks for delivery of materials, and the usage rate is normally 25 devices a week. The ordering cost per order is $4.80 and the carrying cost per device per year is $.80.
Required:
a Calculate the economic order quantity using the EOQ formula.
b Calculate the order point.
c When should S. Patak place the next order if the lead time happened to be 5 weeks and the inventory contains an amount equivalent to the economic order quantity? pg74
Fantastic news! We've Found the answer you've been seeking!
Step by Step Answer:
Related Book For
Cost Accounting Concepts And Applications For Managerial Decision Making
ISBN: 9780070103108
2nd Edition
Authors: Ralph S. Polimeni, James A. Cashin, Frank J. Fabozzi, Arthur H. Adelberg
Question Posted: