The following information relates to the cost records of a company. The total number of direct labour
Question:
The following information relates to the cost records of a company.
The total number of direct labour hours were 50,000 involving 20,000 machine hours. What should be the price quoted for a job involving 2,000 labour hours@ Rs. 3 per hour, 1000 machine hours and Rs. 10,000 in direct materials if the profi t desired is 20% on the selling price?