The standard cost card reveals the following: Labour rate = Re 1 per hour Hours set per

Question:

The standard cost card reveals the following:

Labour rate = Re 1 per hour Hours set per unit for production = 10 hours The actual dates are as follows:

Units produced = 1,000 Hours worked = 12,000 Actual labour cost = Rs. 15,000 Calculate labour variances.