VRV Ltd. furnishes you the following information relating to Process C for the month of December 2009:
Question:
VRV Ltd. furnishes you the following information relating to Process “C” for the month of December 2009:
(i) Opening WIP – Nil.
(ii) Units introduced – 10,000 units @ Rs. 3 per unit.
(iii) Expenses debited to the process: Direct material –
Rs. 14,650; Labour – Rs. 21,373; Over-heads –
Rs. 41,775.
(iv) Normal loss in process – 1% of input.
(v) Closing WIP – 350 units.
Degree of completion: Materials – 100%; Labour &
Overheads – 50%.
(vi) Finished output – 9,500 units.
Degree of completion of abnormal loss: Materials –
100%; Labour & Overheads: 80%.
(vii) Units scrapped as normal loss were sold at Re 1 per unit.
(viii) All the units of abnormal loss were sold at Re 2.50 per unit.
Prepare
(a) Statement of equivalent production.
(b) Statement of cost of fi nished goods; Abnormal loss and closing WIP.
(c) Process C Account.
(d) Abnormal loss account.
Step by Step Answer: