A company has the following production planned for the next four weeks. The figures reflect the full
Question:
A company has the following production planned for the next four weeks. The figures reflect the full capacity level of operations. Planned output is equal to the maximum demand per product.
The direct labour force is threatening to go on strike for two weeks out of the coming four. This means that only 2160 hours will be available for production rather than the usual 4320 hours.
lf the strike goes ahead, which product or products should be produced if profits are to be maximized?
(a) DandA
(b) BandD
(c) Donly
(d) BandC (2 marks)