The following data are to be used for sub-questions (i) and (ii) below: Budgeted labour hours
Question:
The following data are to be used for sub-questions (i) and (ii) below:
Budgeted labour hours ‘ 8500 Budgeted overheads " $148750 Actual labour hours 7928 Actual overheads £146 200
(i) Based on the data given above, what is the labour hour overhead absorption rate?
(a) £17.50 per hour
(b) £17.20 per hour
(c) £18.44 per hour
(d) £18.76 per hour
(ii) Based on the data given above, what is the amount of overhead under- overabsorbed?
(a) £2550 under-absorbed
(b) £2529 over-absorbed
(c) £2550 over-absorbed
(d) £7460 under-absorbed
(3 marks)
CIMA Stage 1