Suppose that a raw material has a lead time of three days and that the average usage
Question:
Suppose that a raw material has a lead time of three days and that the average usage of the material is twelve units per day. What is the reorder point? If the maximum usage is fifteen units per day, what is the safety stock? LO5
Fantastic news! We've Found the answer you've been seeking!