Following is information about Foresters Furnitures direct labour hours and wages last period. Actual labour hours at
Question:
Following is information about Forester’s Furniture’s direct labour hours and wages last period.
Actual labour hours at the standard price per hour...........................................................$2,184
Actual labour hours at the actual price per hour.................................................................2,278
Standard labour hours at the standard price per hour........................................................2,275
Standard labour hours at the actual price per hour............................................................2,373
Required:
A. Calculate the direct labour efficiency variance.
B. Calculate the direct labour price variance.
C. Provide one possible explanation for each variance.