A flood control project at Pleasant Valley dam is projected to cost ($2),000,000 today, have annual maintenance

Question:

A flood control project at Pleasant Valley dam is projected to cost \($2\),000,000 today, have annual maintenance costs of \($50\),000, and have major inspection and upkeep after each 5-year interval costing \($250\),000. If the interest rate is 10 percent/year, determine the capitalized cost.