The variable cost of producing specialty value-added stainless-steel tubing varies according to the quantity produced per year.
Question:
The variable cost of producing specialty value-added stainless-steel tubing varies according to the quantity produced per year. The variable cost is \(\$ 500\) per ton from 0 to 700 tons. Above this level, the variable cost is different. At this time, we are producing 600 tons per year, and the average cost per ton is \(\$ 800\). Next year, we anticipate ramping up production to 1,000 tons, and the projected average cost for all 1,000 tons will be \(\$ 710\) per ton.
a. What is the current fixed cost?
b. If the fixed cost holds constant next year, what is the variable cost of production for tons above 700 tons?
Fantastic news! We've Found the answer you've been seeking!
Step by Step Answer:
Related Book For
Principles Of Engineering Economic Analysis
ISBN: 9781118163832
6th Edition
Authors: John A. White, Kenneth E. Case, David B. Pratt
Question Posted: