You are working with the project team to create the WBS. There are some elements in the

Question:

You are working with the project team to create the WBS. There are some elements in the WBS that can’t be broken down yet. You and the team elect to break down these items later in the project as more details become available.

This approach to creating the WBS is also known as what?

A. Decomposition B. 8/80 Rule C. Parkinson’s law D. Rolling wave planning