An engineer must decide between two ways to pump concrete to the top of a seven-story building.
Question:
An engineer must decide between two ways to pump concrete to the top of a seven-story building. Plan 1 requires the leasing of equipment for $60,000 initially and will cost between $0.40 and $0.95 per metric ton to operate, with a most likely cost of $0.50 per metric ton. The pumper is able to deliver 100 metric tons per 8-hour day. If leased, the asset will have a contract period of 5 years. Plan 2 is rental option that will cost $15,000 per year. In addition, an extra $15 per hour labor cost will be incurred for operating the rented equipment per 8-hour day. Which plan should the engineer recommend if the equipment will be needed for 50 days per year? The MARR is 12% per year.
MARRMinimum Acceptable Rate of Return (MARR), or hurdle rate is the minimum rate of return on a project a manager or company is willing to accept before starting a project, given its risk and the opportunity cost of forgoing other...
Fantastic news! We've Found the answer you've been seeking!
Step by Step Answer:
Related Book For
Question Posted: