Pollution control equipment for a pulverized coal cyclone furnace is estimated to cost $190,000 two years from

Question:

Pollution control equipment for a pulverized coal cyclone furnace is estimated to cost $190,000 two years from now and an additional $120,000 four years from now. If Monongahela Power wants to set aside enough money now to cover these future costs, how much must be invested at an interest rate of 8% per year, compounded semiannually?