The SEWA (Southwestern Electricity and Water Authority) authorized construction projects totaling $1.07 million to improve desalinization plant
Question:
The SEWA (Southwestern Electricity and Water Authority) authorized construction projects totaling $1.07 million to improve desalinization plant efficiency and salinity reduction technology for reject chemicals. Three bids from potential vendors were received in the amounts of $1.06, $1.053, and $1.045 million. Assume the savings will be realized immediately for each bid, were it accepted. Use an expected life of 10 years and i = 6% per year to do the following for the savings anticipated from the lower-than authorized bids:
(a) Determine the equivalent present worth of the savings.
(b) Determine the equivalent annual worth of the savings.
(c) Develop a column chart for the equivalent annual worth for the savings for each bid.