7 When a manager is asked to justify a new budget proposal on the basis of projected...

Question:

7 When a manager is asked to justify a new budget proposal on the basis of projected activities rather than as an incremental adjustment to the prior year's budget, this is an example of

(a) zero-based budgeting

(b) strategic planning

(c) operational planning

(d) contingency planning