Suppose a project actually requires 12 months to complete. Which do you think is likely to cost

Question:

Suppose a project actually requires 12 months to complete. Which do you think is likely to cost more:

(a) having an official schedule of 11 months with at least a 1-month overrun or

(b) having an official schedule of 13 months and, following Parkinson’s Law, having the project take 13 months?

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

Experiencing MIS

ISBN: 9780132667166

3rd Edition

Authors: David Kroenke

Question Posted: