Andrews and Co. Ltd has been invited to tender for a contract. It is to produce 10,000
Question:
Andrews and Co. Ltd has been invited to tender for a contract. It is to produce 10,000 metres of an electrical cable in which the business specialises. The estimating department of the business has produced the following information relating to the contract:
l Materials: The cable will require a steel core, which the business buys in. The steel core is to be coated with a special plastic, also bought in, using a special process. Plastic for the covering will be required at the rate of 0.10 kg/metre of completed cable.
l Direct labour:
Skilled: 10 minutes/metre Unskilled: 5 minutes/metre The business already holds sufficient of each of the materials required, to complete the contract. Information on the cost of the inventories is as follows:
Steel core Plastic
£/metre £/kg Historic cost 1.50 0.60 Current buying-in cost 2.10 0.70 Scrap value 1.40 0.10 The steel core is in constant use by the business for a variety of work that it regularly undertakes.
The plastic is a surplus from a previous contract where a mistake was made and an excess quantity ordered. If the current contract does not go ahead, this plastic will be scrapped.
Unskilled labour, which is paid at the rate of £7.50 an hour, will need to be taken on specifically to undertake the contract. The business is fairly quiet at the moment which means that a pool of skilled labour exists that will still be employed at full pay of £12 an hour to do nothing if the contract does not proceed. The pool of skilled labour is sufficient to complete the contract.
Required:
Indicate the minimum price at which the contract could be undertaken, such that the business would be neither better nor worse off as a result of doing it.
AppendixLO1
Step by Step Answer: