11..Good Progress SpA entered into a contract on 1.1.20X0 at a contract price of 1,000,000 and an...

Question:


11..Good Progress SpA entered into a contract on 1.1.20X0 at a contract price of 1,000,000 and an estimated total profit of 250,000. The contract was due for completion on 31.12.20X4.

The following information was available.

As at 31.12.20X0:

The contract was 25% complete and an architect’s cer tificate was issued for 250,000.

As at 31.12.20X1 The contract was 40% complete and an architect’s cer tificate was issued for 400,000.

Required:

Prepare the income statement entries for the years ended 31 December 20X0 and 20X1 and the balance sheet entries as at those dates.

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

Financial Accounting And Reporting

ISBN: 9780273712312

12th Edition

Authors: Barry Elliott, Jamie Elliott

Question Posted: